Vacuum Vessel Manufacture

Prototype vessel 20° sector
Trial manufacture of outboard
sector without port stubs
(January 2010)
|

Start of series manufacture of production
40 degree inboard sectors
(February 2010)
|

Trial welding of port stub
(February 2010)
|

Welded port stub and ribs of trial
manufacture of outboard upper sector
(March 2010)
|

Welding of ribs on series production inner sector
(March 2010)
|

Welding of ribs on trial inboard curved sector
(March 2010)
|

Completion of welding of first production
inboard 40 degree sector
(May 2010)
|

Completion of upper half of
outboard 20 degree trial sector
(May 2010)
|

Welding trials of upper half of
complete vessel sector
(July 2010)
|

Completion of vacuum vessel assembly building
(August 2010)
|

Vacuum vessel assembly building interior
(August 2010)
|

Half sector delivery to assembly building
(September 2010)
|